Restoration of essential WASH infrastructure

Progetto concluso

Large parts of the Ukrainian territory in the North of the country have been occupied by Russian Forces during several weeks and re-taken in April by the Ukrainian army and made destruction visible and accessible. The direct action will provide specific equipment and repair, as well as coordination capacities for urban and rural Vodakanals in the two oblasts of Chernihiv and Sumy.

Paese/Regione Tema Periodo Budget
Ucraina
Acqua
nothemedefined
Approvvigionamento idrico
Igieniche d'aqua
Diplomazia e sicurezza dell'acqua
20.06.2022 - 31.12.2023
CHF  3’600’000
Contesto

The Russian military attack on Ukraine started on 24th of February 2022. While currently main hostilities concentrate to the Eastern areas of Ukraine, the Northern occupied territories have been largely re-taken by Ukrainian forces. As a result of hostilities and occupation until end of March, a substantial part of essential water supply and sewage infrastructure is destroyed. Shocks through detonations, shelling, and moving tanks in the streets affected in particular sewage collectors, drinking water supply networks, and other underground-infrastructure such as pumping- and lifting stations leaving hundreds of thousands of people without access to safe water supply and sewage removal in their houses.

The project area of concern is the Newly Accessible Area in Chernihiv and Sumy Oblast in North-East of Ukraine where many cities are heavily affected. The probability of a new major attack on these areas is estimated to be rather low as the major area where hostilities take place is concentrated in Eastern Ukraine.

Obiettivi The overall goal of the intervention is to restore and improve the access to safe drinking water and sanitations services of the affected population.
Gruppi target
  • City councils / Vodakanals of Sumy and Chernihiv Oblast
  • Approximately eight war-affected municipalities in Chernihiv and Sumy Oblasts
Effetti a medio termine
  • Urban water institutions of the two cities of Sumy and Chernihiv have improved resilience to maintain their water infrastructure
  • Existing water supply systems in small cities and villages across Sumy and Chernihiv Oblasts can rely on restored water and sanitation infrastructure
Risultati

Risultati principali attesi:  

  • Supply of equipment and machinery for network failure detection and reparation works to Vodakanals within Chernihiv and Sumy Oblast, including the thorough training on the modern equipment. Minor emergency reparation works can be funded through the project
  • Restoration of damaged WASH infrastructure in rural municipalities. Capacity building for the technical departments focussing on project identification, design, tendering and supervision of the execution works


Risultati fasi precedenti:   An initial assessment of the destruction and needs took place in the beginning of May 2022 by an expert team of the Swiss Embassy HA Unit. Most important needs were identified within water and sewage networks which have been destroyed to a large extent.


Direzione/Ufficio responsabile DSC
Partner del progetto Partner contrattuale
ONG internazionale o straniera
Organizzazione svizzera senza scopo di lucro
  • HELVETAS Swiss Intercooperation
  • Other international or foreign NGO North
  • Corpo svizzero di aiuto umanitario
  • City councils and Vodakanals of Chernihiv and Sumy Oblasts; Municipalities in the rural area of Chernihiv and Sumy Oblasts; DESPRO (former SDC Decentralization NGO)


Coordinamento con altri progetti e attori WASH cluster, UNICEF, ICRC
Budget Fase in corso Budget Svizzera CHF    3’600’000 Budget svizzero attualmente già speso CHF    3’640’382 Progetto totale dalla prima fase Budget inclusi partner del progetto CHF   3’600’000
Fasi del progetto Fase 3 15.01.2025 - 31.12.2027   (Fase in corso) Fase 2 21.06.2023 - 31.03.2025   (Fase in corso)

Fase 1 20.06.2022 - 31.12.2023   (Completed)